The work is progressing at SAFRA Public Transport Equipment

The platform that will soon receive the 80 x 15m tent was finalized last week.

The latter will be able to accommodate the first TER AGC trainset from the Occitanie region on January 4, 2021. With this trainset, the SAFRA teams will be able to start their renovation work.

This project: the earthworks, the lime treatment, the dry and wet networks as well as a finiton in hot asphalt were entirely realized by the company Spir Batignolles/ Malet within the expected time.

Now it is up to the company Lauralu Industrie to take over with the implementation of the capital this week. Completion of this work is scheduled for December 3, 2020.